Comment stsetch2 SNF 2012-04-25 18:00:22: Update RF generator
One of the generators has been repaired and is ready for shipment. Before MKS can ship the unit, they wanted and email from Stanford procurement which states that it is OK to send an invoice that is less than the PO amount. Mary sent an email today to MKS. If all goes well, the generator will ship out tomorrow from NY and be here on Monday. It will take about 4-6 hours to install.